Contract Award - Flat Roof Replacement Works at 88-91, 106-108 and 155-186 Shawbridge
October 23, 2025 Deputy Leader and Portfolio Holder for Housing (Cabinet member) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to address water ingress, improve thermal efficiency, and ensure regulatory compliance at 88-91, 106-108, and 155-186 Shawbridge, a contract for £396,194.1 was awarded to Highview Group Ltd., subject to contract and leasehold consultation, utilizing the JCT Intermediate Building Contract (2024) with Contractor’s Design and the Council’s standard Schedule of Amendments.
Full council record
Decision
RESOLVED
that a contract be awarded in the final sum of
£396,194.1 to Highview Group Ltd. (Company Number 10349320)
“subject to contract and leasehold consultation”. The
contractor will be engaged using the JCT Intermediate Building
Contract (2024) with Contractor’s Design, and the
Council’s standard Schedule of Amendments.
Reasons for the decision
Undertake work to resolve the
problems the blocks have had with water ingress and ensure
compliance with Part B and L of the Building Regulations. The work
will contribute to reducing future maintenance needs and improve
thermal efficiency. Highview Ltd submitted the most advantageous
tender.
Alternative options considered
Do nothing: Withdrawing the work would result in continued
deterioration of the building. While ongoing maintenance would
still be required, key fire safety recommendations would remain
unaddressed, exposing the Council to potential legal non-compliance
with statutory obligations, including:
·
Landlord and Tenant
Act 1985
·
Homes (Fitness for
Human Habitation) Act 2018
·
Housing Act 2004
(HHSRS)
·
Regulatory Reform
(Fire Safety) Order 2005
·
Building Safety Act
2022
·
Fire Safety (England)
Regulations 2022
·
Decent Homes
Standard
Partial or Reduced Scope: Undertaking works in phases risks
non-compliance with health and safety legislation and increases
overall costs due to site set ups, welfare, other contractor
prelims, and management costs. A full package of works offers
greater cost efficiency.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 23 Oct 2025 |