OD/26/09 Ellenbrook Play Area Improvement
July 2, 2026 Officer Decision (Officer) Approved View on council websiteFull council record
Purpose
On 8 February 2022, Executive authorised funding for a new five year £3.5m investment programme in play areas (including additional funding from Section 106 planning agreements)
On 8 March 2022, Executive adopted the Play Area Strategy 2022 - 2027 and Play Area Action (Investment) Plan 2022 - 2027 and that the Parks and Cemeteries Operations Manager be authorised to take all necessary steps to deliver the improvement works necessary and replace the play areas identified.
Ellenbrook Park is a Play Area is identified as a site to be replaced in as part of this programme.
Decision
To award a contract to Kompan Ltd.
Reason:
To supply play equipment and associated safety surfacing for the play area improvements.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 2 Jul 2026 |