OD/23/102 Eastern Gateway Roundabout Contract Variation
February 19, 2024 Officer Decision (Officer) Approved View on council websiteFull council record
Purpose
Ipswich Borough Council is currently preparing
to deliver a new roundabout as part of the Eastern Gateway
development, under phase 2c. An Openreach major fibre optic cable
has been identified and requires diverting to enable the roundabout
construction.
A full detailed survey has been carried out by
Openreach, the estimated cost to reroute the existing
infrastructure is £341,073.66 (899256/KJ/C4).
There are sufficient funds available within
existing agreed capital budgets.
A decision has therefore been made to agree a
Variation with the existing groundworks contractor for the
roundabout construction, to include the works for Openreach.
Decision
To vary the contract with the existing main
works contract.
Reason:
To enable delivery of the Phase 2c
Infrastructure (roundabout) at Eastern Gateway and to progress the
Openreach works.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 19 Feb 2024 |