Quarterly budget monitoring
September 5, 2024 Executive (Other) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to approve the recommendations regarding the quarterly budget monitoring, including noting the forecast outturns for the General Fund, Collection Fund, and HRA, agreeing to virements, budget adjustments, and capital reprofiling, and noting progress on budget savings and the capital programme.
Full council record
Content
1.To note the
breakdown of the forecast General Fund
outturn by variance at Appendix 1 and
service area at Appendix 2 of the report of the Executive Member
for Finance and Performance.
2.To note the
forecast outturn 2024/25 General Fund position.
3.To note, and
where necessary agree, the virements and budget
adjustments.
4.To note the
Collection Fund estimated outturn position for council tax and
national non-domestic rates.
5.To note progress
on delivering the 2024/25 agreed budget savings.
6.To note the HRA
forecast outturn.
7.To note the
forecast capital outturn at Q1 of £291.627m for 2024/25 which
includes an overspend of £0.300m on the revised 2024/25
budget and the revised multi-year capital programme and how it will
be financed.
8.To agree the
requested capital reprofiling with future financial years and
budget adjustments, and to note the further capital reprofiling and
budget adjustments which will be reported to Full Council for
agreement via the paper Capital Programme 2024/25 Quarter 1 Budget
Changes on 19th September 2024.
9.To agree changes
in capital financing for ongoing schemes which will lead to a net
reduction in the borrowing requirement of the capital programme by
£0.135m.
10.To note, and where necessary, agree to debt
write-offs
AGREED RECOMMENDATIONS
– as detailed in the report
– as detailed in the report
– none
Related Meeting
Executive - Thursday, 5th September, 2024 7.00 pm on September 5, 2024
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 5 Sep 2024 |
| Subject to call-in | Yes |