Constructing Highways Salt Store, Apex Industrial Estate, Hythe Road - Contract Award Report ED5014622
November 5, 2026 Executive Director of Environment and Resident Services (Officer) Unknown View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
The Executive Director of Environment and Resident Services agreed to approve raising a Task Order under the Council’s contract with FM Conway Ltd for detailed design and enabling works for a new Highways Salt Store. The Task Order is for £250,000 excluding VAT and has an estimated construction period of two to three months. The Executive Director also approved the amount assigned for contingencies.
Full council record
Purpose
Contract Award Report to build a new Highways Salt Store at Hythe Road, replacing the old Salt Store at Lots Road, Chelsea Creek.
Decision
The Executive Director has AGREED to:
- Approve raising a Task Order under the Council’s contract with its contractor, FM Conway Ltd, to complete the detailed design and undertake the enabling works referenced in Section 4 of this report through the issue of a task order using the Council’s existing NEC4 Highways Maintenance and Projects Term Contract (lot 3).
- Approve the Task Order referred to in the previous recommendation for a value of £250,000 excluding VAT (£300,000 including VAT) and for an estimated 2 to 3 months construction period.
- Approve the amount assigned for contingencies set out in the exempt from publication (Part B) Appendix One.
Details
| Outcome | Awaiting Implementation |
| Decision date | 5 Nov 2026 |
| Expected date | 1 Mar 2027 |
| Originally due | 19 Aug 2026 |
| Lead officer | Christian Harris |