Delivering Green Roots awarded grant funding at Lancaster West Estate, Henry Dickens Estate and Allom & Barlow House ED_KD8000008
November 4, 2026 Executive Director of Environment and Resident Services (Officer) Key decision Unknown View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
The Executive Director of Environment and Resident Services agreed to approve the procurement strategy for Phase 1 and Phase 2 of the Pathways to Nature project. This decision was made on 04/11/2026. The decision also delegates the award of contracts for each phase to the Neighbourhood Director of Lancaster West and Grenfell Housing Services.
Full council record
Purpose
This decision is part of the orginal decision - Accepting and delivering Green Roots awarded grant funding at Lancaster West Estate, Henry Dickens Estate and Allom & Barlow House, in Notting Dale Ward KD8000008. The same details apply.
Decision
The Executive Director has AGREED to:
- Approve the Procurement Strategy to undertake competitive Open Tender procedures for both Phase 1 and 2 of the Pathways to Nature: Restoring Garden Estate on Notting Dale, for an expected total value excluding VAT of £521,848 (£657,217.60 including VAT) with the breakdown of costs for each procurement as set out in the exempt from publication (Part B) appendix.
- Delegate the award of contracts for each phase, following receipt of tenders and the completion of evaluation, to the Neighbourhood Director of Lancaster West and Grenfell Housing Services.
Details
| Outcome | Awaiting Implementation |
| Decision date | 4 Nov 2026 |
| Expected date | 21 Oct 2026 |
| Originally due | 21 Oct 2026 |
| Lead officer | James Caspell, Sarah Cross |