Our Cultural Heart (OCH). Phase 1 - Extend the Pre-Construction Services Agreement (PCSA) period - Instruct further demolition works under the PCSA

July 6, 2024 Strategic Director for Growth and Regeneration (Officer) Approved View on council website
Full council record
Purpose

The contractor (BAM) is
already working under the PCSA to deliver the RIBA 4 stage design,
negotiate the construction contract and the associated contract sum
and carry out the already instructed enabling works.
 
The PCSA period is to be
extended by three weeks to the 2nd August 2024 to allow
the construction contract to be concluded.
 
At the same time, to utilise
the contractor resources efficiently and to maintain the programme,
further demolition works are to be instructed under the PCSA. These
works are part of the demolition works that were intended to be
carried out during the next stage of the delivery programme under
the construction contract.
 
Funding of
£396,071 to cover both these
items will be drawn from the approved construction stage budget as
per the current cashflow.
 
This decision takes effect
from the 15th July 2024.
 

Content

To extend the PCSA period to
the 2nd August 2024 and to instruct further demolition
works under the PCSA as part of the enabling works.
 

Details

OutcomeRecommendations Approved