S278 Lytham Road Warton - Additional Funds
January 7, 2025 Director of Highways and Transport (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to bring an additional £173,179 into the Capital Programme to cover unforeseen costs incurred by the contractor on the S278 works on Lytham Road Warton, enabling the county council to complete payments.
Full council record
Purpose
As part of S278 works the highway alignment at
the junction of A584 Lytham Road and Church Road Warton was
modified. Due to unforeseen circumstances additional works were
required and as a result of this additional money is required from
the developer to complete payments to the contractor.
Content
Ridwan Musa, Head of Highway Operations and
Design, on behalf of Matt Townsend the Director of Highways and
Transport took a decision to bring an additional amount of
£173,179 into the Capital Programme to cover the additional
costs incurred by the contractor on the S278 works on Lytham Road
Warton. This will allow the county council to complete payments to
the contractor.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 7 Jan 2025 |