...to approve the reallocation of £9841.46 from a completed retaining wall project to several other completed bridge maintenance projects to reconcile their finances before the end of the financial year, with no change to the overall approved budget.

Full council record
Purpose

Proposed amendments to the
Highways, Bridges Maintenance Capital Programme
Executive Summary.
 
Head of Service is asked to
approve the reallocation of funds within the above programme to
allow projects to be closed and financially reconciled ahead of the
Financial Year end. The amounts detailed will allow outstanding,
unprocessed cost items costs to be settled. Details of the proposed
reallocations are as follows:
 
Transfer a total of
£9841.46 from completed project id 14935 24/25 30423 Church
Brow Retaining Wall to the following projects to allow them to be
reconciled
£1000 to project 12764
22/23 6602 Peel Road
£2000.23 to project 12780
22/23 4661 Yorkshire Street Aqueduct
£300 to project 12779
22/23 1000B Carr Road Canal
£3500 to project 13984
23/24 6188 Worsley Park
£325.31 to project 11454
21/22 Moor Street Railway Bridge
£2715.92 to project 13990
23/24 1072 Grindleton
The reallocations are between
completed projects in the same programme and there is no change to
the total approved budget.
 
Background
Budget allocations are
regularly reviewed to ensure the programme is delivered within
available resources and completed project budgets
reconciled.
Consultations
N/A
Risk management
The changes are required to
ensure that the budget is managed effectively.
Financial
There is no change to the
approved programme budget. This item does not require cabinet
approval.
Christopher Wilding
Bridges and Structures Design
Manager
27th March 2025.
 

Content

John Davies, Head of
Highway Network Management, on behalf of the Matt
Townsend, Director of Highways and
Transport, took a decision to approve changes
to the Bridges Maintenance Capital programme detailed in this
report.