Schools Condition Led Programme - Lancaster Bowerham Primary School Removal of Asbestos Insulation residues

June 27, 2025 Director of Growth and Regeneration (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to approve an additional £5,625.00 from the Schools Condition Led Programme's contingency balance to cover a budget shortfall for asbestos residue removal at Lancaster Bowerham Primary School.

Full council record
Purpose

A decision on the Schools Condition
Led Programme (CLP) to approve the removal of asbestos residues
from the plant room in the main school building.

Content

Michael Peppin, Capital Programme Manager,
on behalf of the Simon Lawrence, Director of Growth
and Regeneration and Sarah Robinson, Head of Property Service, took
the decision as set out in the report.

Supporting Documents

Report.pdf

Details

OutcomeRecommendations Approved
Decision date27 Jun 2025