Director of Highways and Transport, Enda Garvey, approved amendments to the Highways, Bridges Maintenance Capital Programme on 6th October 2026. The decision approved the reallocation of £50,000 from a completed project at Calder Vale to an ongoing project in the Trough of Bowland. This reallocation is to fund additional essential works at Sykes Farm and Blaze Moss.

Full council record

Purpose

As part of the normal process of service delivery, the approved highways capital programme now requires amendments to allow effective delivery the Programme.

Head of Service is asked to approve the reallocation of residual funds from a completed project at Calder Vale to an ongoing project in the Trough of Bowland.

Request details:
Transfer £50,000

From
Completed project: ID 17035 26/27 Calder Vale Road - Barnacre-with-Bonds - Adjacent to 1-2 Victoria Terrace

To
In progress project: ID 17034 26/27 Sykes Farm Retaining Wall 32995 and Blaze Moss Culvert.


The reallocation is between projects in the same programme and there is no change to the total approved budget.

The changes are required because additional work is required to complete essential works at Sykes Farm and Blaze Moss.

This item does not require cabinet approval.

Christopher Wilding
Bridges and Geotechnical Design Manager
6th October 2026
 

Decision

Enda Garvey, Interim Head of Highways Operations and Design has taken a decision to approve the proposed amendments to the Highways, Bridges Maintenance Capital Programme. 