A601(M) Maintenance Project

December 1, 2022 Cabinet (Cabinet collective) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

Lancashire Cabinet approved recommendations on 01/12/2022. The decision was to retain and repair Higher North Road bridge as the lowest cost option for the A601(M) Maintenance Project, while seeking to deliver other original project aspects.

Full council record

Purpose

The funding of the A601(M) bridge and highway maintenance project was approved by Cabinet in July 2020. This was the lowest cost option for maintenance of the A601(M) over a 30-year period and included revoking the motorway status, reducing the speed limit and the replacement of Higher North Road bridge with an at grade junction as a means of achieving this.

It has now been found that the estimated cost of the new junction has increased significantly due to construction inflation adversely affecting the activities associated with that part of the project. It is now proposed to retain and repair Higher North Road bridge, that now being the lowest cost option within budget, whilst seeking to deliver the other aspects of the original project.

This is deemed to be a Key Decision and the provisions of Standing Order C19 have been complied with.

Decision

The Cabinet approved the recommendation(s) as set out in the report.

Details

OutcomeRecommendations Approved
Decision date1 Dec 2022
Effective from7 Dec 2022