Proposed 2023/24 Highways New Start Capital Programmes

March 2, 2023 Cabinet (Cabinet collective) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

Lancashire Cabinet approved recommendations on 02/03/2023. The decision approved the addition of £28.811 million in grant funding for highway maintenance to the capital programme and approved detailed programmes of work. This includes a £1.865 million externally funded programme utilising recycled pavement materials and a £1 million addition to fix road defects.

Full council record

Purpose

This report recommends approval of the addition of the Department for Transport's indicative 2023/24 grant funding allocation for Highway Maintenance, that is £28.811 million, to the highway block of the capital programme once confirmed. The report also recommends the proposed apportionment of this assumed level of funding set out at Appendices 'A' and 'B'. The reference to New Starts refers to this "new" funding.

The report also requests approval of detailed programmes of work relating to this funding set out at Appendices 'C' to 'H'. Any revisions required on receipt of the confirmed funding envelope will be developed and presented for approval at a future date.

The report also requests approval of a programme of work with value of £1.865 million that is externally funded via the redevelopment of the Samlesbury Enterprise Zone. This programme will utilise recycled pavement materials from the site that would otherwise have to be disposed of. The proposed programme is detailed at Appendix 'I'

A carbon statement for the carriageway capital programme has been produced which shows a saving of 769 tonnes which is a 28% saving compared with a programme based on traditional material choices. This is detailed at Appendix 'J'.

The report also requests approval to add £1 million, approved by Full Council on 9 February 2023, to the Highways Block of the Capital Programme to fix multiple defects on roads which would otherwise have to wait for repair.

This is deemed to be a Key Decision and the provisions of Standing Order C19 have been complied with.

Decision

Cabinet approved the recommendation(s) as set out in the report.

Details

OutcomeRecommendations Approved
Decision date2 Mar 2023
Effective from8 Mar 2023