Redistribution of capital funding to offset overspends within the 24/25 P2 Drainage Defect & 25/26 Drainage Defects projects
March 12, 2026 Director of Highways and Transport (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
The Director of Highways and Transport approved the reallocation of £0.11m in capital funding on 12/03/2026. Funds will be transferred from 24/25 P2 Drainage Defect projects and 25/26 Drainage Defects projects to offset overspends in 25/26 CAT 2 (Contract) Structural Defects projects.
Full council record
Purpose
Reallocate capital underspends of £0.11m to offset projected overspends in the 25/26 CAT 2 (Contract) Structural Defects projects.
Funds will be transferred among the following projects to offset overspends within the 24/25 P2 Drainage Defect & 25/26 Drainage Defects projects.
24/25 P2 Drainage Defect projects (£0.03m) – PPMS IDs: 15827; 15828; 15829; 15830; 15831; 15833; 15834; 15835
25/26 Drainage Defects projects (£0.08m) – PPMS IDs: 16298; 16299; 16300; 16303; 16304; 16306; 16308; 16310; 16314; 16318
Decision
Kirstie Williams, Interim Head of Service – Highways Operations & Design, on behalf of the Matt Townsend, Director of Highways and Transport, took a decision to approve the reallocation of funds as set out in the report.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 12 Mar 2026 |