Design & Cost Report for S278 Highway Works Associated with the Construction of 129 dwellings at Land off Main Street, Carlton, WF3 3RW.
Director of City Development (Officer) Approved View on council websiteFull council record
Content
The Chief Officer (Highways and
Transportation) has:
a. Noted the detail of the highway works described in the Design
and Cost report and shown on the S278 Works Plan attached at
Appendix 3;
b. Given authority to negotiate the terms of and enter into an
agreement with the developer under the provisions of Section 278 of
the Highways Act 1980; whereby the works associated with the
development are carried out by the developer and overseen by the
Council;
c. Given authority to incur expenditure of £5000 staff
checking and inspection fees to be fully funded by a developer
through a Section 278 Agreement.
d. Approved the adoption of new highway as per the area highlighted
in red as shown on drawing number E22/7918/023_03 attached at
Appendix 3 so that it can be added to the Council’s
maintenance regime;
e. Requested the City Solicitor to advertise a Draft Traffic
Regulation Order (TRO) to provide no waiting at any time
restrictions (double yellow lines); and if no valid objections are
received, to make, seal and implement the new TRO as
advertised.
Supporting Documents
Details
| Outcome | Recommendations Approved |