a.  Note the contents of
the Report to the Chief Officer (Highways and Transportation)
(“the Report”);
b.  Note that full
Council (21.2.2024) within the Capital Programme Update for 2023-28
has injected £5,404,000 of City Region Sustainable Transport
Funding and £511,488 of Section 106 funding to deliver the
scheme;
c.  Note and
approve the proposed layout as per the drawings attached to the
Report;
d.  Give authority to
advertise a Traffic Regulation Order and, subject to objections,
request the City Solicitor to make, seal and implement the
Order;
e.  Give authority to
display notices on site under the provision of Section 23 of the
Road Traffic Regulation Act 1984 to inform the public of the
proposed formal pedestrian crossings;
f.  Approve the
construction of cycle tracks under the powers contained under the
provisions of Section 65(1) of the Highways Act 1980 for segregated
or shared use by pedal cyclists and pedestrians;
g.  Approve the
construction of traffic calming measures under the powers contained
under the provisions of Section 90 of the Highways Act 1980;
and
h.  Give authority to
tender for a contractor to deliver the scheme utilising the
Intermediate Works Contractor Framework.
 
 

Content

The Chief Officer Highways and Transportation
has:
a.  Noted the contents
of the Report to the Chief Officer (Highways and Transportation)
(“the Report”); 
b.  Noted that full
Council (21.2.2024) within the Capital Programme Update for 2023-28
has injected £5,404,000 of City Region Sustainable Transport
Funding and £511,488 of Section 106 funding to deliver the
scheme; 
c.  Noted and
approved the proposed layout as per the drawings attached to the
Report; 
d.  Given authority to
advertise a Traffic Regulation Order and, subject to objections,
request the City Solicitor to make, seal and implement the
Order; 
e.  Given authority to
display notices on site under the provision of Section 23 of the
Road Traffic Regulation Act 1984 to inform the public of the
proposed formal pedestrian crossings; 
f.  Approved the
construction of cycle tracks under the powers contained under the
provisions of Section 65(1) of the Highways Act 1980 for segregated
or shared use by pedal cyclists and pedestrians; 
g.  Approved the
construction of traffic calming measures under the powers contained
under the provisions of Section 90 of the Highways Act 1980;
and
h.  Given authority to
tender for a contractor to deliver the scheme utilising the
Intermediate Works Contractor Framework. 

Supporting Documents

APPENDIX B.pdf
APPENDIX A.pdf
APPENDIX C.pdf
REPORT.pdf
APPENDIX D.pdf
APPENDIX E.pdf
SIGNED DECISION RECORD.pdf

Details

Decision date4 Apr 2024
Effective from12 Apr 2024
Subject to call-inYes