District Heating Update - Investment Plans

March 13, 2024 Executive Board (Committee) Key decision Approved View on council website
Full council record
Purpose

Executive Board will
be recommended to:

Approve the Wellington Street extension construction
works, subject to approval of the Green Heat Network Fund
application, for commencement in Summer 2024

Note the business case which supports these works
included in this report

Note the more detailed financial model which
supports these works included as Confidential Appendix 1

Approve the early instruction of works on Castle Street based on
the business case outlined in this report

Approve the commencement of a procurement exercise to support the
South Bank Heat Network project

Supporting Documents

District Heating Report Appendix 4 280224.pdf
District Heating Report Appendix 2 EDCI 280224.pdf
District Heating Report Appendix 3 280224.pdf
District Heating Cover Report 280224.pdf

Details

OutcomeRecommendations Approved
Decision date13 Mar 2024
Subject to call-inYes