Council Housing Growth Programme: Approval to place orders with statutory utilities providers for the diversions of existing utilities and the installation of new utility services at the Hough Top Court site in order to secure infrastructure timescal

November 14, 2023 Director of City Development (Officer) Approved View on council website
Full council record
Content

The Chief Asset Management and Regeneration
Officer has:
a) Approved the placing of early orders with statutory utilities
providers for the diversions of existing utilities and the
installation of new utility services at the Hough Top Court site in
order to secure infrastructure timescales, to the value of
£438,567.80 inclusive of contractors management fees as set
out by the Scape Framework and LCC contingency.

Supporting Documents

REPORT TO THE DECISION MAKER.pdf
SIGNED DECISION RECORD.pdf

Details

OutcomeRecommendations Approved
Decision date14 Nov 2023