Meanwood District Centre
June 26, 2023 Director of City Development (Officer) Key decision Awaiting outcome View on council websiteFull council record
Purpose
The junction works involve the introduction of
wider footways, signalised junctions and crossings and a cycle lane
across the border of two wards at a cost of £700,000.
Content
The Chief Officer
(Highways and Transportation) was requested to:
a)
Note the content of this report.
b)
Approve the detailed design and implementation of a
package of highway works for the Meanwood District Centre, as shown
on drawing 2434-LCC-00-XX-DR-TM-01_01c (Appendix A).
c)
Note and approve the total cost of £740,000
comprising of £506,000 Works costs, £105,000 UTMC,
£126,000 Staff fees and £3,000 legal fees, and give
authority to incur the expenditure, which is to be funded from the
S106 contributions, CRSTS funding and Leeds City Councils, Town and
Local Centres Programme.
d)
Instruct the City Solicitor to advertise a Traffic
Regulation Order to introduce waiting restrictions, a movement
order to implement prohibited vehicle movement turns and a speed
limit order to introduce a 20-mph speed limit as
shown on the attached drawing no.
2434-LCC-00-XX-DR-TM-TRO_01 (Appendix B) & SLO_01 (Appendix
C)
e)
If no valid objections are received, to instruct the
City Solicitor to subsequently make, seal and implement the Traffic
Regulation Order, Movement Order and Speed Limit Order as
advertised.
Supporting Documents
Details
| Decision date | 26 Jun 2023 |
| Effective from | 4 Jul 2023 |
| Subject to call-in | Yes |