Leeds Station Sustainable Travel Gateway – Approval to vary the Network Rail Basic Asset Protection Agreement and Funding From Network Rail Agreement
Director of City Development (Officer) Approved View on council websiteFull council record
Content
The Chief Officer for Asset Management and
Regeneration approved:
a) A variation to the Network Rail BAPA to include the Mill Goit
works
b) A variation to the Network Rail Funding Agreement by increasing
the costs of the Mill Goit design and construction works by
£272,500, costs which have been identified during the Mill
Goit design works
c) Injection and authority to spend of £272,500 into the
capital programme for the additional construction costs to the
scheme funded from Network Rail
d) A variation to the Engineering and Construction contract with
the Balfour Beatty to reflect the required increase in Public
Liability Insurance for the Mill Goit.
e) A variation to the Engineering and Construction contract with
Balfour Beatty to reflect the required increase in Public Liability
Insurance for the Mill Goit
Supporting Documents
Details
| Outcome | Recommendations Approved |