Summary

...to approve the A52 Leverton and Haltoft End resurfacing scheme, authorize a procurement process for its delivery, and delegate authority to the Executive Director – Place to make decisions necessary to progress the scheme, including contract awards.

Full council record

Decision

1.   
That the Executive Councillor for Resources approves the Scheme for
resurfacing works at A52 Leverton and Haltoft End (Scheme) as
detailed in the report.

 
2.   
That the Executive Councillor for Highways and Transport:

 

i)     
Approves the undertaking of a procurement process for delivery of
the Scheme; and
 

ii)    
Delegates authority to the Executive Director – Place, in
consultation with the Executive Councillor for Highways and
Transport, to take all decisions necessary to progress the Scheme
up to and including determination of the final form contracts and
the award and execution of those contracts and other documentation
necessary to deliver the Scheme resulting from the procurement
process.

Reasons for the decision

As detailed in the report

Alternative options considered

As detailed in the report

Supporting Documents