North Hykeham Relief Road (NHRR) - Scheme Update and Full Business Case (FBC) Submission

September 2, 2025 Executive (Other) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to progress the North Hykeham Relief Road (NHRR) scheme, the Executive delegated authority for various actions, including considering additional cost information, approving the Full Business Case submission in principle, finalizing the Full Business Case for submission to the Department for Transport, and accepting funding from the Department for Transport, contingent on the final grant being no less than £110.045m, while also recommending that the Council approve an additional £13.98m financial contribution to the scheme.

Full council record

Decision

  1. That authority be delegated to the Leader of the Council to consider additional information regarding the increased Anglian Water costs and bat mitigation before the Council confirms its budget setting for the Capital Programme and agrees the additional financial contribution of £13.98m for the North Hykeham Relief Road Scheme (NHRR).
  2. That the submission of the Full Business Case to the Department for Transport be approved in principle.
  3. That authority be delegated to the Executive Director – Place, in consultation with the Executive Councillor for Highways and Transport, to take all necessary decisions and determine the final form of the Full Business Case for the NHRR Scheme to be submitted to the Department for Transport, as detailed in the report.
  4. That the acceptance, in principle, of funding from the Department for Transport for the purposes of delivering the NHRR scheme, provided that the final grant, which will be subject to conditions, is no less than the current funding allocation of £110.045m, be approved.
  5. That authority be delegated to the Executive Director – Place, in consultation with the Executive Councillor for Highways and Transport, to take all necessary decisions in relation to the grant of funding from the DfT, including agreement of the DfT’s funding conditions, in order to accept and secure the funding grant as soon as possible.

Related Meeting

Executive - Tuesday, 2nd September, 2025 10.30 am on September 2, 2025

Supporting Documents

OSMB Statement on North Hykeham Relief Road.pdf
North Hykeham Relief Road - Scheme Update and Full Business Case.pdf

Details

OutcomeRecommendations Approved
Decision date2 Sep 2025