Children and Young People's Supported Accommodation from April 2027
December 16, 2025 Executive Councillor: Children's Services (Other) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...the recommended future model of supported accommodation was approved, including commissioning a Youth Housing Service and solo accommodation, continuing an Open Select List for Independent Supported Accommodation, and developing a business case for new in-house accommodation.
Full council record
Decision
1.
That the recommended future model of supported accommodation, as
set out in the report, be approved.
2.
That the undertaking of a procurement to commission the following,
be approved:
i.
A Youth Housing Service for a contract term of a maximum of five
years (three years with an option to extend for up to two further
years) and for the whole life value of approximately £10.49
million.
ii.
Solo accommodation in Lincolnshire (two Lots) for a contract term
of five years (three years with an option to extend for up to two
further years) and for the whole life value of approximately
£3.548 million per Lot. If solo
accommodation can be commissioned sooner, the end date would align
to the end of the Youth Housing Service.
3.
That authority be delegated to the Executive Director of
Children’s Services in consultation with the Executive
Councillor for Children’s Services, to take all decisions
necessary to progress the procurement up to and including
determination of the final form contract and the award and
execution of contract and any other documentation necessary to
deliver the procurement.
4.
That the continued operation of an Open Select List as detailed in
the report to purchase Independent Supported Accommodation
placements where necessary be approved.
Reasons for the decision
As detailed in the report
Alternative options considered
As detailed in the report
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 16 Dec 2025 |