Lincoln Castle Repairs Phase 1– Construction – RIBA 5-7

July 24, 2026 Executive Director - Place (Officer) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Executive Director - Resources approved the signing of a Licence to Operate document for solar panel installation at Leslie Manser Primary School on 27/07/2026. This licence allows Solar for Schools to install, operate, and maintain solar panels for 25 years. The school will pay for consumed electricity at a rate that increases annually with RPI, and excess energy will be sold by the PV asset owner.

The Greater Lincolnshire Combined County Authority approved its Calendar of Meetings for the remainder of 2025/26 and for 2026/27 on 17/09/2025. Authority was delegated to the Monitoring Officer to amend the calendar as required.

The Greater Lincolnshire Combined County Authority endorsed the administration of the GLCCA Development Fund on 17/09/2025. This fund will support preliminary work for strategic projects and programmes, with an initial annual sum of £500,000. Applications will be assessed by a Technical Officer Group with recommendations made to the Mayor and Chief Operating Officer.

The Executive Councillor for Resources and the Executive Councillor for Children's Services approved the construction of a new standalone drama facility at Spalding Academy Secondary School on 01-08 May 2026. This facility will provide two drama studios and ancillary areas to support an increase in the school's net capacity by 110 places. The scheme will be procured under the Pagabo Construction Framework.

The Executive Councillor for Highways and Transport approved the proposed Traffic Regulation Order for bus stop clearways on Main Road, Hundleby on 22 May - 3 June 2026. This order was recommended for approval by the Planning and Regulation Committee after considering objections.

The Greater Lincolnshire Combined County Authority appointed Chairs for its Transport Board, Business and Infrastructure Board, Employment and Skills Board, Economic Advisory Panel, Audit Committee, and Overview and Scrutiny Committee on 03/06/2026. The Mayor was appointed as the Co-opted Member for the Transport for the North Partnership Board and Rail North Committee, and nominations were sought for a member to sit on the Humber Bridge Board.

Full council record

Purpose

Entering into the contract will enable:-

• Vital repairs to Lincoln Castle Walls
• The management of safety and conservation risks relating to condition deterioration.

Decision

This Statement of Decision concerns Lincoln Castle Wall Repair Project – Phase 1 (as described in the approved Executive report).
Purcell have been used as a specialist heritage professional services provider for the Castle Walls project. They have been in contract for the preconstruction (design) stage, and a decision is now sought to enterinto a Professional Service Contract for the construction stage of Phase 1 to enable seamless professional services support for Phase 1 of the Castle Repairs Project.

Approval is sought to award the following contract :-
A Professional Services Contract (PSC) to Purcell Architecture Ltd – Architect Masterplanners and Heritage Consultants.

The PSC with Purcell will be accessed by direct award via the Pagabo framework – Lot 15.
This contract is a standard NEC4 form of contract, with standard Z / boilerplate Clauses that have been recommended by Legal Services concerning GDPR, modern slavery etc.

The PSC scope includes the following specialist services/consultancy/ surveys:-

• Architectural and Heritage
• Structural Engineering
• Heritage Sector Cost consultancy
• Ecology
In relation to the following scope of repairs to the:

• East Wall
• Observatory Tower
• Lucy Tower
• Stone masonry repairs across the internal walls

Further detail on the delivery scope may be found in the report to the Executive of 8 April 2026.

Full Council approved a capital budget of £1.9 million for the Lincoln Castle Wall Repairs project on 20 February 2026. The costs for this contract will be met from this approved budget.

Alternative options considered

Do nothing - This option is not recommended as future repair works are needed to manage safety and conservation risks. Risk impact includes:-
• impact on public safety
• potential partial/ closure of the site,
• impact on events, public and Crown Court access
• non-compliance with conservational statutory duties.
Delay or omission of these works could also lead to prolonged stonework exposure and further condition deterioration, a subsequent increase in volume of repairs
being required and increased capital costs over time.

Supporting Documents

Calendar of Meetings - Authority GLCCA.pdf
Development Fund Fund.pdf
Calendar of Meetings - Authority GLCCA.pdf
Appendix B 2026-27.pdf
Appendix A 2025-26.pdf
Appendix B 2026-27.pdf
GLCCA Development Fund - Appendix A Draft Guidance.pdf
Development Fund Fund.pdf
GLCCA Development Fund - Appendix A Draft Guidance.pdf
Appendix A 2025-26.pdf
Appendix A - Project Visuals.pdf
Spalding Academy - Drama extension.pdf
Hundleby Main Road.pdf
CCSC Statement on Spalding Academy.pdf
AGM Appointment of Chairs and Outside Bodies.pdf
AGM Appointment of Chairs and Outside Bodies.pdf
Review of Financial Performance 202526.pdf
West Willoughby A153.pdf
Reprocurement of the HWRC Management Contract.pdf
ESC Statement on HWRC Contract.pdf
Item 3 - Housing Strategy GLCCA BI Report July 2026 FINAL.pdf
Appendix A - Draft Housing Strategy.pdf
Appendix A - Draft Housing Strategy.pdf
Replacement table on page 41 of the DRAFT Housing Strategy.pdf
Item 3 - Housing Strategy GLCCA BI Report July 2026 FINAL.pdf
Replacement table on page 41 of the DRAFT Housing Strategy.pdf
West Willoughby A153.pdf

Details

OutcomeRecommendations Approved
Decision date24 Jul 2026
Effective from3 Jul 2026
Lead officerDave Pennington