June 17, 2024 Executive Councillor: Highways, Transport and IT, Leader of the Council (Executive Councillor: Resources, Communications and Commissioning) (Cabinet member) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to approve the Hawthorn Road shared footway and cycleway scheme, authorize a procurement process for its construction, and delegate authority to the Executive Director – Place to make necessary decisions for the scheme's progression and contract execution.
Full council record
Decision
1.
That the Leader of the Council (Executive Councillor for Resources,
Communications and Commissioning) approves the scheme for the
construction of the Hawthorn Road shared footway and cycleway
(Scheme) as detailed in the report.
2.
That the Executive Councillor for Highways, Transport and IT
approves the undertaking of a procurement process for construction
and delivery of the scheme; and
3.
That authority be delegated to the Executive Director –
Place, in consultation with the Executive Councillor for Highways,
Transport and IT, to take all decisions necessary to progress the
Scheme, up to and including the determination of the final form of
the contract and the award and execution of the contract and such
other documentation necessary to deliver the Scheme.
Reasons for the decision
As detailed in the report
Alternative options considered
As detailed in the report
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 17 Jun 2024 |