Corporate Performance Year-End 2025/26
June 10, 2026 Executive (Other) Approved View on council websiteFull council record
Purpose
The purpose of the report was to present an overview of corporate performance at Year-End 2025/26, including progress against Executive actions, delivery of the Council Plan 2024–27, the Strategic Risk Register, programme and project management, and wider compliance measures.
Decision
ORDERED that Executive:
- Approve the proposed changes to Executive actions as detailed at Appendix 1.
- Approve the proposed changes to the Council Plan 2024–27 supporting workplan actions as detailed at Appendix 3.
AGREED that Executive:
- Note the delivery status of the Council Plan 2024–27 supporting workplan as detailed at Appendix 2.
- Note the progress and position of the corporate performance disciplines.
- Note that, following agreement of the refreshed Council Plan 2026–29, activities in the work plan would be embedded within Directorate Plans once developed.
- Note the Strategic Risk Register as detailed at Appendix 4.
Reasons for the decision
REASONS
The decisions were taken to enable the Executive to effectively discharge its performance management responsibilities, in line with the Council’s Local Code of Corporate Governance.
Alternative options considered
OPTIONS
Executive considered the option of not operating a performance management framework. This was not supported, as such an approach would place the Council at risk of failing to meet its statutory Best Value duty.
Related Meeting
Executive - Wednesday, 10 June 2026 - 5.00 pm on June 10, 2026
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 10 Jun 2026 |
| Effective from | 20 Jun 2026 |
| Expected date | 10 Jun 2026 |
| Originally due | 10 Jun 2026 |
| Lead officer | Ann-Marie Johnstone |
| Subject to call-in | Yes |