Update on Capital Work Programme

November 11, 2024 Margam Crematorium Joint Committee (Committee) Approved View on council website
Full council record
Content

Decision

 

 

·       Concrete repairs as per estimate received - £125,000
to £150,000 excluding access.

 

·       Redecoration in masonry paint internal estimate
£80,000 excluding access.

 

·       A full refurbishment of the existing toilets as they
are currently laid out fitting waterproof wall panels, resin flooring and
improving the ceiling insulation.

 

·       Redevelopment of the internal courtyard, remembrance
garden and installation of exit canopy.

 

 

 

 

Supporting Documents

Report of the Technical Officer.pdf
Asset Condition Report 2024 - Margam Crematorium.pdf

Details

OutcomeRecommendations Approved
Decision date11 Nov 2024