Planning permission for application reference 2024/0930/01/DET be granted:
 
 i. 
Subject to a section 106 agreement to
secure:
· 
Training employment plan with monitoring fee -
£1,800; 
· 
SuDS Maintenance – with monitoring fee of
£10,000;
· 
Implementation of improvements to the service yard
access gates and Management Plan for access to the service
yard;
· 
Implementation of noise mitigation
measures.
 
ii. 
Subject to the following conditions:
 
1. 
3 years;
2. 
Approved plans;
3. 
Restrict the length of stay of guests;
4. 
Details of cycle parking to be submitted;
5. 
Implementation of noise mitigation measures in
accordance with Noise Assessments and supplementary
information;
6. 
Buffer zone as shown on approved plan not to be used
as sleeping accommodation for guests;
7. 
Requirement for units to meet NR15 noise;
8. 
Details of all materials;
9. 
Details of works to and management of access gates
to service yards;
10.TEMP;
11.Construction
Method Statement;
12.Refuse –
implementation of refuse storage;
13.No external
refuse outside of the premises;
14.Implement
Delivery, Servicing and Waste Management Strategy; 
15.Further details
of drainage components;
16.Further details
of the green roof;
17.Groundwater
monitoring throughout the construction of the development;

18.Verification that
SUDs has been implemented in accordance with approved plans;

19.Lighting
strategy;
20.Security
strategy;
21.Window
schedule;
22.Details of
internal doors/architraves;
23.Protection of
Nesting Birds;
24.Bat Working
Method Statement;
25.further details
of PVs.

 
iii. 
Listed Building Consent for application reference
2024/0943/01/LBC be conditionally approved subject to the
following conditions:

 
1. 
3 years;
2. 
Approved plans;
3. 
Large scale details of secondary glazing;
4. 
Details of internal doors and
architraves.
 

iv. 
It was also agreed that in the event that a
satisfactory section 106 agreement covering the issues raised above
is not received by 31st August 2026 that the
application be refused for its failure to make adequate provision
in this regard contrary to Policy DEL1 of the CSUCP unless an
extension of time is agreed to the satisfaction of
the Assistant Director Planning in consultation with the
Chair and Vice Chairs of the Planning
Committee. 

 

v. 
It was also agreed that delegated authority
be given to the Assistant Director Planning, in
consultation with the Chair and Vice Chairs of Planning
Committee, to amend, add or omit conditions and
heads of terms of the section 106 legal agreement, where
appropriate, to ensure the application complies with relevant
development plan policies and national planning
guidance. 

Related Meeting

Planning Committee - Friday 13th February, 2026 10.00 am on February 13, 2026

Supporting Documents

7.1 TJ Hughes - PLAN.pdf
7. TJ Hughes - FINAL.pdf

Details

OutcomeRecommendations Approved
Decision date13 Feb 2026