PCC26/22 Modification to Consultancy Contract in relation to DECS25/18 Springwell Solar Farm NSIP

September 7, 2026 Assistant Director of Planning and Climate Change (Officer) Awaiting outcome View on council website
Full council record

Purpose

Authority to modify the existing consultancy contract and Purchase Order in relation to DECS25/18 Springwell Solar Farm NSIP to extend the contract to the post-decision stage

Decision

That approval is given to:

  1. Appoint Kirkstone Planning and Regeneration as case officer to undertake post-decision duties (discharge of Requirements) in relation to the Springwell solar farm Development Consent Order.
  2. Transfer the Kirkstone Planning and Regeneration consultancy contract underspend against the examination phase of the Springwell Solar Farm NSIP into the post-permission phase.

Supporting Documents

PCC2622 Modification to Consultancy Contract in relation to DECS2518 Springwell Solar Farm NSIP.pdf

Details

OutcomeFor Determination
Decision date7 Sep 2026