Approval to Extend S38 Agreement - North of Turnstone Drive, Scunthorpe

November 20, 2025 Director: Communities (Other) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to ensure the continuation of a valid Section 38 agreement for the residential development north of Turnstone Drive, Scunthorpe, the completion date was extended from November 30, 2025, to November 30, 2027, without changing the supporting bond amount.

Full council record

Decision

Authorisation was given to extend the
completion date of the Agreement under Section 38 of the Highways
Act 1980 for the residential development off Lakeside, North of
Turnstone Drive, Scunthorpe from 30 November 2025 to 30 November
2027 without amendment to the amount of supporting bond.

Reasons for the decision

The completed S38 Agreement supports
development and permits the council to adopt the roads, footways,
verges, swales, and highway drainage once the development is
completed to the council's requirements.

The S38 Agreement can only legally last for two years and requires
an extension of time if works aren't complete at the end of the two
year period. This development is not yet completed and the
agreement needs renewing.

Alternative options considered

Not applicable

Supporting Documents

Decision Report North of Turnstone Drive - Extension Nov 2027.docx.pdf

Details

OutcomeRecommendations Approved
Decision date20 Nov 2025