Approval to extend Completion Date of the Agreement Under Section 38 of the 1980 Highways Act
February 11, 2026 Director: Communities (Other) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to extend the completion date of the Section 38 Highways Act agreement for the residential development off land at the West of Roman Way, Scunthorpe, from 28 February 2026 to 28 February 2028, without changing the supporting bond amount.
Full council record
Decision
Authorisation given to extend the completion
date of the Agreement under Section 38 of the Highways Act 1980 for
the residential development off land at the West of Roman Way,
Scunthorpe from 28 February 2026 to 28 February 2028 without
amendment to the amount of supporting bond.
Reasons for the decision
The completed S38 agreement support
development and permit the Council to adopt the roads, footways,
verges, swales, and highway drainage once the development has been
completed to the council’s requirements.
The S38 agreement can only legally last for two years and requires
an extension of time if works aren’t complete at the end of
the two year period. This development is not yet completed, and the
agreement needs renewing.
Alternative options considered
N/A.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 11 Feb 2026 |