BUDGET MONITORING Period 6 2026/27

November 2, 2026 Cabinet (Cabinet collective) Approved View on council website
Full council record

Decision

RESOLVED to recommend to Full Council:

a)      Note the contents of the report and the current budget monitoring position.

b)      Approval to increase the 2026/27 capital budget for Housing S106 Enabling by £131,000 to £1,120,000. To be funded by S106 contributions.

c)       Approval to rename the North Walsham 3G Pitch capital project to Fakenham 3G Pitch for 2026/27. Also to increase the capital budget to £1,228,476 following grant award, total project funding £878,889 grant and £349,587 borrowing.

d)      Approval to increase the 2026/27 capital budget for Fakenham Sports Decarbonisation by £25,000 to £539,300. To be funded by the Council’s Net Zero Reserve.

e)      Approval to increase the Cromer 3G Pitch capital budget by £6,872 to £16,872. To be funded by borrowing.

f)        Approval to increase the Purchase of Bins 2026/27 capital budget £75,000 to £302,517. To be funded by Council Capital Receipts.

g)      To acknowledge the S151 approval of £32,599 towards the Rocket House 2026/27 capital budget, in order to meet requirements arising from legal covenants, from the Asset Management Reserve. To also seek approval of £50,000 towards the Rocket House 2026/27 capital budget from borrowing. Total increases of £82,599.

h)      Approval to increase the Public Conveniences Renovation, Holt Country Park capital budget by £20,000 to a total of £70,000. To be funded by Capital Receipts.

i)        Approval to increase the Newgate Lane, Wells, Public Conveniences capital budget by £6,380 to a total of £46,380. To be funded by Capital Receipts.

j)        Approval to increase the Chalet Refurbishment capital budget by £100,000 to a total updated budget of £206,260. To be funded by Borrowing.

k)       Approval to increase the Sunken Gardens Improvements, Marrams, Cromer capital budget by £160,000 to a total of £307,000. To be funded by Borrowing.

l)        Approval to increase the Fakenham Connect Roof and Fire Doors capital budget by £62,000 to a total of £160,000. To be funded by Borrowing.

m)     Approval to increase the Dr’s Steps, Cromer capital budget by £75,000 to a total of £145,000. To be funded by Borrowing.

n)      Approval to increase the NNDC Cromer Office Solar Panels capital budget by £100,000 to a total of £160,000. To be funded by Borrowing.

o)      Approval to increase the Melbourne Slope, Cromer Public Realm & Shelter capital budget by £70,000 to a total of £100,000. To be funded by Borrowing.

p)      Approval to increase the Coastwise capital budget by £3.960m to a total of £18.570m. To be funded by Capital Grants

q)      Approval to transfer the balance of £150,000 from the Environment reserve to the Net Zero Reserve

r)  Approval to reinstate the £60,000 annual contribution to the elections reserve, following the recent LGR announcement.

Reasons for the recommendations:

To update members on the current budget monitoring position for the Council.

Related Meeting

Cabinet - Monday, 2nd November, 2026 10.00 am on November 2, 2026

Supporting Documents

Appx D Reserve Statement Monitoring 2026-27.pdf
Appx B Resources - Updated.pdf
Appx B Service Delivery.pdf
Appx C Capital Programme 2026-27 - Updated.pdf
Budget Monitoring Report P6 2026-27 draft - Updated.pdf
Appx A General Fund Summary P6 2026-27.pdf
Appx B Corporate.pdf

Details

OutcomeRecommendations Approved
Decision date2 Nov 2026