REPORT OF THE DEPUTY LEADER AND CABINET MEMBER FOR CORPORATE SERVICES
September 12, 2023 Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
Northumberland Cabinet approved the use of £1.855 million from contingency to fund pay award shortfalls, re-profile £15.902 million to the Capital Programme, and transfer £1.556 million from the Public Health grant reserve. These decisions were made on 12/09/2023.
Full council record
Decision
Financial Performance 2023-24 – Position at the end of June 2023
RESOLVED that:-
(a) Cabinet :
- Approve the use of £1.855 million from contingency to partly fund the shortfall in the expected cost of pay awards for 2023-24.
- Approve the re-profiling to the Capital Programme of £15.902 million from 2023-24 to 2024-25 to reflect estimated expenditure levels in the current financial year.
- Approve the transfer of £1.556 million from the Public Health main grant reserve to provide additional services to reduce poverty and health inequalities.
(b) Cabinet note:
- the projected overspend on services of £4.115 million and the assumptions outlined in the report.
- the projected net overspend of £4.471 million after accounting for outstanding inflationary pressures and the utilisation of the Exceptional Inflation Reserve and contingency. The financial monitoring process is a continuous process, and it is not unusual to predict an overspend in the first formal monitoring report as pressures in the system are recognised and realised. Services are now taking appropriate action to bring the budget back into balance and corporately work is underway to ascertain if rising interest rates will ensure a favourable return to the Council and improve the position further. An updated position for the 6 months to September 2023 will be presented to Cabinet on 12 December 2023.
- the supplementary estimates at Appendix A and the required changes to the budgets.
- the delivery of the approved savings at Appendix B.
- the use of the contingency shown at Appendix L.
- the use of reserves shown at Appendix M.
- the virements requested by services shown at Appendix O.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 12 Sep 2023 |