Seeking exemption to Contract Procedure Rules for the implementation of maintenance scheme on the Pennine Way

August 22, 2023 Executive Director for Place & Economic Growth (Officer) Approved View on council website
Full council record
Purpose

To seek approval for exemption from CPR with
the aim to deliver a specialist scheme of works on the Pennine Way
by CPY Excavations

Content

RESOLVED - That:
Exempt Contract Procedure Rules and approve the direct award of a
contract to CPY Excavations - Due to the time restraints and
required specialist knowledge and operations it is recommended to
proceed with CPY Excavations as the designated contractor with a
proven history of similar schemes

Reasons for the decision

Undertake an open quotation process in
accordance with Contract Procedure Rules - Due to the time
restraints and required specialist knowledge and operations it is
highly unlikely to source an alternative contractor with the
necessary knowledge and experience of delivering this scheme.

Alternative options considered

Not applicable

Details

OutcomeRecommendations Approved
Decision date22 Aug 2023