Alexandra Park Boathouse - WC Refurbishment
August 11, 2023 Director of Economy (Officer) Approved View on council websiteFull council record
Purpose
Approval is required to fund the associated
cost of refurbishment works to Alexandra Park Boathouse WC facility
from the Corporate Landlord Capital Budget. The proposed work has
been estimated at £55,000. The proposed refurbishment work
includes reconfiguration of the facility and creating access
between the WC and adjoining Café to enable controlled
access and use.
Content
RESOLVED - That:
To approve the associated funding of £55,000
from the Corporate Landlord Capital Budget.
This will allow the continued use of the WC
facility, whilst bringing it to current standards,
improving utilisation, security and operational
management.
The fees connected to this proposal are £3.5k,
bringing the total proposal to £58.5k.
Details
| Outcome | Recommendations Approved |
| Decision date | 11 Aug 2023 |