Creating a Better Place – Spindles Enabling Works 1 Variation 8 - Early Procurement of Site Accommodation for Market, Events and Archive
April 12, 2023 Cabinet Member - Culture and Leisure, Cabinet Member - Finance, Corporate Services and Sustainability and Deputy Leader, Leader of the Council and Cabinet Member for Growth, Chief Executive, Director of Finance, Director of Legal Services, Executive Director for Place & Economic Growth (Cabinet member) Key decision Approved View on council websiteFull council record
Purpose
In February 2022 Cabinet approved a
Pre-Construction Services Agreement (PCSA) contract to be entered
into
On 25th July Cabinet gave approval to split workstreams for the
Spindles Redevelopment into Project 1 (demolition of TJ Hughes,
construction of a new market and events space and works to the
roof) and Project 2 (redevelopment of internal retail units to
create workspace).
As a result of this, an instruction is required for the Stage 5
design fees
Content
RESOLVED - That:
Option 1 is recommended to allow the programme to progress in line
with current agreed programme dates.
Reasons for the decision
Option 1 – progress as set out within
this report and uplift the value of PCSA to enable Willmott Dixon
to maintain programme and progress the Stage 5 design
Option 2 – Place the works on hold until Main Works contracts
are in place for the Market, Events and Archive
Alternative options considered
Option 2.
Details
| Outcome | Recommendations Approved |
| Decision date | 12 Apr 2023 |
| Subject to call-in | Yes |