Creating a Better Place – Spindles Enabling Works 1 Variation 7 - Early Procurement of Site Accommodation for Market, Events and Archive

April 12, 2023 Cabinet Member - Culture and Leisure, Cabinet Member - Finance, Corporate Services and Sustainability and Deputy Leader, Leader of the Council and Cabinet Member for Growth, Chief Executive, Director of Finance, Director of Legal Services, Executive Director for Place & Economic Growth (Cabinet member) Approved View on council website
Full council record
Purpose

On 25th July Cabinet gave approval to split
workstreams for the Spindles Redevelopment into Project 1
(demolition of TJ Hughes, construction of a new market and events
space and works to the roof) and Project 2 (redevelopment of
internal retail units to create workspace).
An Enabling Works contract was entered into relating to Project 1,
referred to as Enabling Works 1 (EW1).
To maintain programme, it is necessary to ensure the site setup is
suitable for the number of staff involved in piling, mine workings,
M

Content

RESOLVED - That:
Option 1 is recommended to allow the programme to progress in line
with current agreed programme dates.

Details

OutcomeRecommendations Approved
Decision date12 Apr 2023
Subject to call-inYes