Seeking exemption to Contract Procedure Rules for the implementation of maintenance scheme at Castleshaw Reservoir on the Pennine Bridleway

August 16, 2024 Director of Environment (Officer) Approved View on council website
Full council record
Purpose

To seek approval for an exemption from the
requirements of Rule 4 of the Contract Procedures Rules (CPRs) with
the aim to deliver a specialist scheme of works on the Pennine
Bridleway by CPY Excavations.

Content

RESOLVED - That:
Utilise Rule 21 of the Contract Procedure Rules and exempt the
requirement under Rule 4 of the CPRs to carry out an open quotation
process. This will enable a direct award of a contract to CPY
Excavations.

CPY Excavations has the required specialist knowledge and
operations to deliver the Council’s requirements and the
Company has a proven history of similar schemes.

Details

OutcomeRecommendations Approved
Decision date16 Aug 2024