Authorisation for Milestone Infrastructure LTD to undertake construction of active travel improvements on Thorpe Wood - NOV23/CAB/55

November 13, 2023 Cabinet (Cabinet collective) Key decision Approved View on council website
Full council record

Purpose

The Cambridgeshire and Peterborough Combined Authority have
successfully been awarded a total of £3,896,59 Active Travel
England as part of Active Travel Funding 4. Peterborough has been
allocated a total of £2,986,590 of which £2,000,000 is
for the construction of Thorpe Wood Cycleway Phase 3.

Decision

Cabinet:
 
1. Authorised the works order of up to £2,000,000 to
Milestone Infrastructure Ltd to undertake construction of active
travel improvements on Thorpe Wood, under the existing Peterborough
Highways Term Services Contract.
 
2. Authorised the Director of Place & Economy to vary the
works order value when required subject to; a. available budget
being in place; b. the total sum of each variation not exceeding
£100,000, c. the combined value of any authorised
variation(s) do not exceed the total sum of £500,000. d. any
variations are to be made in prior consultation with internal
audit, finance and legal services.

Supporting Documents

Authorisation for Milestone Infrastructure LTD to undertake construction of active travel improveme.pdf

Details

OutcomeRecommendations Approved
Decision date13 Nov 2023
Subject to call-inYes