Salford City Council – Record of
Decision
I Councillor Youd, Lead Member
for Finance and Support Services and chairman of the Procurement
Board, accept the recommendation of the Procurement Board and in
exercise of the powers contained within the Council Constitution do
hereby approve:
·
to Award the Contract for design and installation of
roof mounted solar PV on estate and Salford Community Leisure
buildings 2025/26 Programme, as detailed in the table
below:
Detail required
Answers
Title/Description of Contracted
Service/Supply/Project
SCC 2025/26 Solar PV installation
Programme
Procurement Reference numbers (DN and CR
number supplied by Procurement)
DN562301
Name of Successful
Contractor
NPS Solar
Supplier Registration Number
(to be supplied by Procurement
5513604
Proclass
Classification No.
(to be completed by
procurement)
102300
Type of organisation
(to be supplied by
Procurement)
Private Limited Company
Status of Organisation
(to be supplied by
Procurement)
SME
Contract Value (£)
£845,900
per annum
Total contract value £ (including
extensions)
£845,900
total project value
Contract Duration
6 months
Contract Start Date
20/10/2025
Contract End Date
20/04/2026
Optional Extension Period 1
3 months
Optional Extension Period 2
N/A
Who will approve each Extension
Period?
Executive Director (extension <
£150k)
Contact Officer (Name &
number)
Paula Connor-Bennett 0161 686 7413
Lead Service
Group
Place
How the contract was
procured?
(to be supplied by
procurement)
PSR Competitive
Process
Framework Details (where
applicable)
(procurement body, framework
reference & title, start/ end date
GMCA 562301 Go Neutral
Framework
GMCA-FC036-SCC Lot 1
Chest Ref DN562301
Funding
Source
Combination of Above (please detail
below)
Ethical Contractor (EC):
Mayor’s Employment Charter
Yes
EC: Committed to sign The
Mayor’s Employment Charter
Yes
EC: Committed to the principles
outlined in the Mayor’s Employment
charter
Yes
EC: Accredited Living Wage
Employer
Yes
EC: Committed to becoming
Accredited Living wage Employer
Yes
?
The Reasons are:
Salford City Council (SCC) aims
to deliver smart energy systems that will deliver an impact against
the city regions carbon neutral 2038 target, build on the local
economy and make energy supply more affordable for SCC. The
programme is a key part of GMs work to decarbonise its public
estate. Key to achieving this target is increasing investment in
local, smart energy infrastructure.
SCC is seeking to install solar
PV at up to 9 sites across the city as part of its contribution
towards Greater Manchester’s target of becoming a
carbon-neutral city region by 2038. This project would see up to
860kWh of renewable energy generation added to the estate as well
as reducing SCC’s carbon emissions by over 140tCO2e per
annum.
Options considered and rejected
were:
To not undertake the project
would mean the proposed measures at each
site will not contribute towards Salford and Greater
Manchester’s target of becoming a carbon-neutral city region
by 2038. To not undertake the investment would mean lost
opportunity to reduce revenue spend on electricity and reduce
carbon emissions.
Assessment of Risk:
The programme will have a risk
register in place and mitigation measures.
The programme is low risk as
the roof and structural surveys that are to be undertaken will
de-risk the sites by identifying whether they are able to proceed
as planned and highlight any site
constraints.
If we do not take this approach
the risk is that we will delay the installation of additional
renewable energy assets and associated budget and carbon savings
for the council.
The source of funding
is: £845,900 Total
·
£750,000 Invest to Save - Planning Policy and
Climate Change – 2025/26.
·
£ 95,900 – GMCA Mayoral Renewables Fund
Grant Funding.
Legal Advice obtained: Yes.
Financial Advice
obtained: Yes.
Procurement Advice obtained:
Yes.
HR Advice: N/A.
Climate Change Implications
obtained: Yes.
The following documents have
been used to assist the decision process:
·
Greater Manchester 5-year Environment
Plan 2025-2030
·
Procurement Board Request to go out to tender
17th May 2025
Contact Officer:
Paula Connor-Bennett
Telephone number:
0161 686 7413
This matter is also subject to
consider by the Lead Member for Planning, Transport and Sustainable
Development. The Lead Member has been consulted and is supportive
of the proposed contract.
This matter is not subject to
consideration by another Lead Member.
Signed: Cllr J
Youd Dated: 13 October
2025.
Lead Member
FOR DEMOCRATIC SERVICES USE
ONLY:
* This
decision was published on 14
October 2025.
* This
decision will come in force at 4.00 p.m. on 21 October 2025
unless it is called-in in
accordance with the Decision Making Process Rules.
Related Meeting
Procurement Board - Monday, 13 October 2025 2.00 pm on October 13, 2025
Details
| Decision date | 13 Oct 2025 |
| Subject to call-in | Yes |