Proposed Extension to Technical and Highways Works Framework (Sharon Walls)
December 8, 2025 Key decision Awaiting outcome View on council websiteFull council record
Content
Salford City Council – Record of
Decision
I Paul Dennett, City
Mayor, accept the recommendation of the Procurement Board and in
exercise of the powers contained within the Council Constitution do
hereby:
·
to Award the Contract for Technical and Highways
Works Framework, as detailed in the table below:
Detail
required
Answers
Title/Description of Contracted
Service/Supply/Project
Technical and Highways Works Framework
6month Extension
Procurement Reference numbers (DN
and CR number supplied by Procurement)
Name of Successful
Contractor
Name of
Contractor
Type of
Organisation
Registration No
Lot
1 - Minor Civils
-
Argyle NW
Construction Ltd
- Colas
Limited
-
Rosgal Limited
- P
Casey (Land Reclamation) Ltd
-
Bethell Construction Limited
- Eric
Wright Civil Engineering Ltd
-
Limited Company
-
Limited Company
-
Limited Company
-
Limited Company
-
Limited Company
-
Limited Company
-
02829893
-
2644726
-
3731189
-
1122137
-
0264322
-
2565379
Lot
2 – Vehicle
Restraint System
-
Coating Services
Ltd
-
Protek Fencing Ltd
-
Limited Company
-
Limited Company
-
3852483
- 2197089
Lot
3 - Drainage
- Colas
Limited
-
Rosgal Limited
-
General Utilities
Northwest Ltd
- AE
Yates Ltd
-
Bethell Construction Limited
- No
Dig Drainage
Solutions Ltd
-
Limited Company
-
Limited Company
-
Limited Company
-
Limited Company
-
Limited Company
-
Limited Company
-
2644726
-
3731189
-
6468779
-
415632
-
0264322
-
10378682
Lot
4 – Structures & Bridges
- P
Casey (Land Reclamation) Ltd
- Eric
Wright Civil Engineering Ltd
-
Coating Services
Limited
-Amalgamated
Construction Ltd
(trading
as
AmcoGiffen)
- AE
Yates Ltd
-
Bethell Construction
Ltd
-
Limited Company
-
Limited Company
-
Limited Company
-
Limited Company
-
Limited Company
-
Limited Company
-
1122137
- 2565379
-
3852483
-
995892
- 415632
- 0264322
Lot
5 – Coring & Site Investigations
-
Pavement Testing
Services Ltd
-
Construction Testing Solutions Limited
-
Concept Engineering Consultants Ltd
-
Limited Company
-
Limited Company
-
Limited Company
-
04374737
-
05998333
- 03401367
Lot
6 – Landscaping
And
Associated
- P Casey (Land
Reclamation) Ltd
-
Wright Landscapes
Ltd
-
Horticon Ltd
-
Groundwork
Landscape Ltd
-
Landscape
Engineering Ltd
-
Bethell Construction
Ltd
-
Limited Company
-
Limited Company
-
Limited Company
-
Limited Company
-
Limited Company
-
Limited Company
-
1122137
-04611247
-
2463376
-
1339901
-
04049863
-
0264322
Supplier Registration
Number
(to be supplied by
Procurement
Various
Proclass Classification
No.
(to be completed by
procurement)
390000
Type of
organisation
(to be supplied by
Procurement)
Other
Status of
Organisation
(to be supplied by
Procurement)
SME
Contract Value
(£)
£ 10,000,000
per annum
Total contract value £
(including extensions)
£ 40,000,000
Contract
Duration
12 months
Contract Start
Date
06/02/2026
Contract End
Date
05/08/2026
Optional Extension Period
1
6months (Lot 5 only)
Optional Extension Period
2
N/A
Who will approve each Extension
Period?
Executive Director (extension <
£150k)
Contact Officer (Name &
number)
Sharon Walls
Lead Service
Group
Place
How the contract was
procured?
(to be supplied by
procurement)
Other
Framework Details (where
applicable)
(procurement body, framework
reference & title, start/ end date
Open Tender on the
Chest:
Technical
and Highways Works Framework
Funding
Source
Combination of Above (please detail
below)
Ethical Contractor (EC):
Mayor’s Employment Charter
Yes
EC: Committed to sign The
Mayor’s Employment Charter
Yes
EC: Committed to the principles
outlined in the Mayor’s Employment
charter
Yes
EC: Accredited Living Wage
Employer
Yes
EC: Committed to becoming
Accredited Living wage Employer
Yes
The Reasons
for the decision and report is to award a compliant contract that
allows continuity of design and delivery of works to be
commissioned and undertaken by suitably appointed contractors
within the framework. An Exception to award and extension is being
sought.
Options considered and
rejected were
– Salford is in the final year of a 4 year
framework and requires additional time to ensure a compliant and
fit fir purpose new framework is in place going forward.
Alternative frameworks are available including the
Bolton and Manchester Framework however, the availability of
contractors who are already commissioned by other GM authorities
cannot guarantee their commitment to deliver the scale of works
required to be delivered during the extension period and the
working relationships have not been established.
Hence, this was the preferred
procurement route. Work cannot be undertaken in-house as there are
insufficient resources.
Assessment of
Risk
– by not having a contract in place Salford
would not be able to deliver its financial commitments for 2025/26
and also 2026/27. The award of contract for a
further 6months for the current framework is therefore essential in
ensuring that Salford can continue to design and deliver a wide
range of projects that will be funded from the capital and revenue
programmes across the next 2 financial years.
The source of
funding is a mixture of approved capital and revenue funding
depending on the nature of work being undertaken.
Legal Advice
obtained
– The proposed award of
the contract follows a call off exercise in accordance with the
Council’s Technical and Highways Minor
Civils Works Framework as referred to in the
body of the report and legal supports the
award.
Financial Advice
obtained
– Finance identifies the funding that is in
place to deliver the likely projects to be undertaken. There
remains sufficient headroom in the contract for projects to be
commissioned by the council should it be needed.
Procurement Advice
obtained -
Yes.
HR Advice obtained –
N/A.
Climate Change Implications
obtained – N/A.
Contact Officer: Sharon Walls
Telephone number: 07598063732
The appropriate Scrutiny
Committee to call-in the decision is the Growth and Prosperity
Scrutiny Panel
Signed:
Paul
Dennett Dated: 8 December
2025.
City Mayor
FOR DEMOCRATIC SERVICES USE
ONLY:
* This
decision was published on 9 December 2025
* This
decision will come in force at 4.00 p.m. on 16 December 2025 unless it is called-in in
accordance with the Decision Making Process Rules.
Related Meeting
Procurement Board - Monday, 8 December 2025 2.00 pm on December 8, 2025
Details
| Decision date | 8 Dec 2025 |
| Subject to call-in | Yes |