Approval to award contract for Ordsall Chord Riverside Connection Footpath Improvements

August 23, 2023 Approved View on council website
Full council record
Content

Salford City Council – Record of
Decision
 
I Councillor Youd, Lead Member
for Finance and Support Services and chairman of the Procurement
Board, in exercise of the powers contained within the
Council Constitution
do hereby approve:
 
·     
to award the contract
for the Ordsall Chord Riverside Footpath Improvements, as detailed in the table
below:
 

Detail required

Answers

Title/Description of Contracted
Service/Supply/Project

Ordsall
Chord Riverside Footpath Improvements

Name of Successful
Contractor

Landscape Engineering Ltd

Supplier Registration Number

(to be supplied by Corporate
Procurement)

04049863

Type of organisation

(to be supplied by Corporate
Procurement)

Private Limited Company

Status of Organisation

(to be supplied by Corporate
Procurement)

SME

Contract Value (£)

£ 151,869.48

Overall scheme value

£ 187,195.27 / full project
(inclusive of associated supervision fees & risk
allowance)

Contract Duration

13 weeks

Contract Start Date

04/09/2023

Contract End Date

04/12/2023

Optional Extension Period 1

months

Optional Extension Period 2

months

Who will approve each Extension
Period?

Strategic Director (extension <
£150k)

Contact Officer (Name &
number)

Nilima Misra, Perry Twigg

Lead Service Group

Place

How the contract
was procured?

(to be supplied by
procurement)

SCC Technical and Highways Works Framework –
Lot 6 – Landscaping and Associated Services

Framework Details (where
applicable)

(procurement body, framework reference
& title, start/ end date

 

Funding Source

Capital Programme

Ethical Contractor (EC): Mayor’s
Employment Charter

 

EC: Committed to sign Charter

 

EC: Accredited Living Wage
Employer

 
The Reasons are:

·        
Following a fair and transparent open tender process
the recommendation is to award the contract to the above
contractor, Landscape Engineering Ltd. The overall response across
quality, price and social value was of a sufficient standard to
award. The quality and price scores demonstrate a supplier with the
relevant skills and experience to deliver this scheme within the
allocated budget.

·        
To allow the Council’s Technical Services team
to undertake appropriate supervision and management of the contract
works.

·        
To ensure that there is adequate risk provision and
mitigate against construction phase risk.
 
Options considered and rejected
were: Not to award the
contract.
The
project forms part of the package of schemes that constitute a
network of traffic free routes in City Centre Salford and had
received MCF support for its development phase.
Not
awarding the contract would cause a severe delay in the delivery of
the scheme. This project has received significant public and
political interest in recent months with much anticipation to see
this small section of the riverside made safe and finally opened
up.
 
Assessment of Risk: LOW
·        
Funding is available from the Regen Capital
Programme 2023/24
·        
The council’s Technical Services (Engineering
and Landscape Design, Structures, Lighting) teams are experienced
in the design of schemes of this nature.
·        
The contractor is on the council’s existing
Framework and has a successful track record of delivering schemes
of this nature on behalf of the City Council.
 
The source of funding
is SCC Regen Capital Programme
2023/24
 
Legal Advice obtained. Yes – from the Shared
Legal Service
 
Financial Advice
obtained: Yes – from
Alison Woods, Commercial Finance Manager
 
Procurement Advice obtained:
Yes – from Daniel Cunliffe, Procurement Officer 
 
HR Advice obtained –
N/A
 
Climate Change Implications
obtained: Yes
 
The following documents have
been used to assist the decision process.

Report to Procurement
Board dated 23rd August 2023

 
Contact
Officers:             
Nilima Misra
                                           
Perry Twigg     
Tel. 07966 316309  
 
The appropriate Scrutiny
Committee to call-in the decision is the Growth and Prosperity
Scrutiny Panel
 
 

Signed:        Cllr Youd         Dated:    23 August 2023.
           
     Lead
Member
 

FOR DEMOCRATIC SERVICES USE
ONLY
 
*          
This decision was published on 25 August 2023
*          
This decision will come in force at 4.00 p.m. on 4 September 2023
unless it is called-in in accordance with the Decision Making Process Rules.
 

Details

OutcomeRecommendations Approved
Decision date23 Aug 2023
Subject to call-inYes