Greater Manchester Joint Minerals and Waste Plan Update
November 10, 2026 Cabinet (Cabinet collective) Key decision Awaiting outcome View on council websiteFull council record
Decision
Salford City Council - Record of Decision (Cabinet)
I, Paul Dennett, the City Mayor, in consultation with Cabinet in exercise of the powers contained within the City Council Constitution do hereby:
1) Approve the decisions set out in the table at Appendix A;
2) Approve the delegations to AGMA set out in the table at Appendix A; and
3) Approve delegated authority, to the extent not already captured by existing delegations or delegated to AGMA, to the Deputy Chief Executive (Executive Director of Place) to take any executive decisions necessary for the Authority to progress through the plan making stages including those identified in the table at Appendix A.
The Reasons are:
To support the timely production of the Greater Manchester Joint Minerals and Waste Plan
Options considered and rejected were:
Not approving the additional delegations would make it very difficult to produce a joint plan in line with the 30-month timetable set out by government.
Assessment of Risk:
Low. This report relates to the process for producing the plan and additional
delegations for key stages. All 10 Greater Manchester local authorities agreed to the principle of a new GM joint minerals and waste plan and in 2025 as explained in the main body of the report.
The source of funding is:
Budget has been identified by the GMCA to undertake the preparation of the plan and at present this budget is considered to be sufficient to cover all stages of the plan preparation. However, if this position changes, including due to unforeseen circumstances, further reports will be presented.
Legal Advice obtained:
The new plan-making requirements are set out in the Town and Country Planning (Local Planning) (England) Regulations 2026. Statutory Guidance has also been issued.
The content and recommendations in the report reflect those Regulations and Guidance and sets out the steps now required in relation to progressing a joint waste and minerals DPD, including the decisions that need to be made to allow AGMA, as a joint committee of the 10 GM authorities, to formulate and prepare the joint plan.
This report also sets out the decisions that are reserved to each of the Councils, and which cannot therefore be taken by AGMA as a joint committee
Financial Advice obtained:
The GM Joint Minerals and Waste Plan Update is being fully funded by GMCA so there are no financial implications for Salford City Council.
Procurement Advice obtained:
N/A
HR Advice obtained:
N/A
Climate Change Advice obtained:
As part of preparing the plan an integrated assessment will be undertaken throughout the production of the plan which will consider climate change alongside other social, economic and environmental considerations.
The following documents have been used to assist the decision process:
Reports to Cabinet dated 24 June 2025 and Council dated 16 July 2025: Greater Manchester Joint Minerals and Waste Plan: Decision Making Process
Contact Officer: Matt Doherty / Place Directorate
Telephone number: 0161 793 2304
The appropriate scrutiny to call-in the decision is the Growth and Prosperity Scrutiny Committee.
Signed: ____Paul Dennett______________ Dated: 11/11/2026
City Mayor
For Democratic Services use only
This decision was published on 12 November 2026
This decision will come in force at 4.00 p.m. on 19 November 2026 unless it is called-in in accordance with the Decision Making Process Rules.
Appendix A – Proposed Decisions and Delegations
Stage / activity approval is needed for
Regulation
What documents are required at this stage?
Propose to delegate this decision?
Decision / Delegation / To Note
Cabinet delegating to who
Publication of the initial / first timetable
Timetable
No. Covered by recommendation 1 of this report
Decision of Cabinet
Not applicable
Publication of subsequent timetable updates
Timetable
Yes
Delegation
Deputy Chief Executive (Executive Director of Place)
Issuing the notice of intention to commence minerals and waste plan document preparation
Reg.44
Notice of intention to commence
No. Covered by recommendation 1 of this report
Decision of Cabinet
Not applicable
Decision to publish the scoping consultation and any decisions necessary to facilitate that including approving the content of that consultation and the date it will be published
Reg.45
Consultation documents
Yes
Delegation
Deputy Chief Executive (Executive Director of Place)
Gateway 1: Responsibility for preparation and publication of the self-assessment summary, including approval of the self-assessment of readiness for minerals and waste plan document
Reg.46
Self-assessment Summary
Yes
Delegation
Deputy Chief Executive (Executive Director of Place)
Publishing the summary of responses to the scoping consultation
Reg.47
Summary of scoping consultation
Yes
Delegation
AGMA
Publishing the consultation on proposed minerals and waste plan document content and evidence
Reg.48
Consultation documents, including
SEA scoping
Yes
Delegation
AGMA
Publishing the summary of consultation on proposed minerals and waste plan document content and evidence
Reg.49
Summary of consultation
Yes
Delegation
AGMA
Agree preparation of Policies Map
Reg. 50
Map of proposed minerals and waste plan policies
Yes
Delegation
Deputy Chief Executive (Executive Director of Place)
Gateway 2: Submission of the material for advice
Reg.51
Documents to be submitted to the gateway assessor, including:
· Cover letter with summary, issues and list of supporting documents.
· Timetable
· Project Initiation Document (PID)
· Draft Statement of compliance
· Draft Statement of Soundness
Yes
Delegation
Deputy Chief Executive (Executive Director of Place)
Publishing the consultation on the proposed minerals and waste plan document
Reg.52
Consultation documents
Yes
Delegation
AGMA
Publishing the summary of consultation on the proposed minerals and waste plan document
Reg.55
Summary of consultation
Yes
Delegation
AGMA
Gateway 3: Submission of the material for the prescribed requirements assessment (and repeat of Gateway 3 if required)
Reg.56 (Reg.58)
Documents as set out in reg. 57: “prescribed requirements”
No. Full Council decision
To Note
Not applicable
Submission of documents to Secretary of State
Reg.59
· Policies map
· Gateway 3 completion statement
· Summary of consultation
· Representations
· A statement of compliance
· A statement of soundness
· An environmental report
· If applicable, a statement setting out why the plan is unlikely to have significant environmental effects
· Supporting documents
No. Full Council decision
To Note
Not applicable
Publishing the recommendations and reasons of the examiner
Reg.62
Recommendations and reasons of the examiner
No approval needed
To Note
Not applicable
Adoption of a minerals and waste plan document
Reg.64
· The minerals and waste plan
· Adoption Statement
No. Full Council decision
To Note
Not applicable
Related Meeting
Cabinet - Tuesday, 10 November 2026 10.00 am on November 10, 2026
Details
| Reference | 0 |
| Decision date | 10 Nov 2026 |
| Effective from | 20 Nov 2026 |
| Subject to call-in | Yes |