Approval to Award The Contract for Barton Moss Extension Works (Sean Leah)
July 24, 2024 Approved View on council websiteFull council record
Content
Salford City Council – Record of
Decision
I Paul Dennett, City
Mayor, in exercise of the powers
contained within the Council Constitution do hereby approve:
·
to award the contract
for the construction works at Barton Moss, as detailed in the table
below:
Detail required
Answers
Title/Description of Contracted
Service/Supply/Project
Barton Moss – extension to existing
facility
Name of Successful
Contractor
Robertson Construction North West Limited
Supplier Registration Number
(to be supplied by Corporate
Procurement)
12728498
Type of organisation
(to be supplied by Corporate
Procurement)
Private Limited Company
Status of Organisation
(to be supplied by Corporate
Procurement)
SME
Contract Value (£)
£
14,867,516 full construction costs – subject to DfE
funding
Contract Duration
18 months
Contract Start Date
30/09/2024
Contract End Date
31/03/2026
Optional Extension Period 1
Not intended at this stage
Optional Extension Period 2
Not intended at this stage
Who will approve each Extension
Period?
Choose an item.
Contact Officer (Name &
number)
Sean Leah
Lead Service Group
People Services
How the contract was procured?
(to be supplied by
procurement)
Mini Competition
Framework Details (where
applicable)
(procurement body, framework reference
& title, start/ end date
Procure Partnerships Construction
Framework - £5m to
£15m
Funding Source
Grant
Ethical Contractor (EC): Mayor’s
Employment Charter
EC: Committed to sign Charter
EC: Accredited Living Wage
Employer
The Reasons are to appoint a suitably qualified
contractor partner for the construction works at the
centre.
Options considered and rejected
were: None. All procedures are
in accordance with normal standing orders.
Assessment of Risk: High.
The source of funding
is DfE grant, subject to
confirmation of final costs.
Legal Advice obtained: Tony Hatton, Principal
Solicitor
Financial Advice
obtained: Natalie
Birchall, Finance Manager
Procurement Advice obtained:
Deborah Derbyshire, Category Manager
HR Advice obtained:
N/A.
Climate Change Implications
obtained:
No significant Climate Change
implications in this project. All projects are developed to meet or
exceed current legislation and requirements relating to energy
efficiency and carbon reduction targets. Projects are required to
support the Council’s objectives of becoming carbon neutral
by 2038.
The works will
be programmed to minimise the traffic impact in the area. Any waste
materials will be removed and taken to a transfer station for
systematic sorting and recycling to ensure minimal landfill
waste.
Sustainability
plans would be targeted to also align with opportunities to
continue to deliver social value outcomes.
The following documents have
been used to assist the decision process.
The relevant documents contain
exempt or confidential information and are not available for public
inspection.
Contact Officer: Sean Leah
Telephone number:
This matter is also subject to
consideration by the Lead Member for Children’s and Young
People’s Services. The Lead Member has been consulted and is
supportive of the proposed contract.
This matter is not subject to
consideration by another Lead Member.
The appropriate Scrutiny
Committee to call-in the decision is the Growth and Prosperity
Scrutiny Committee.
Signed: Paul
Dennett Dated: 24 July
2024.
City
Mayor
FOR DEMOCRATIC SERVICES USE
ONLY
*
This decision was published on 25 July 2024
*
This decision will come in force at 4.00 p.m. on 1 August 2024
unless it is called-in in accordance with the Decision Making
Process Rules.
Details
| Outcome | Recommendations Approved |
| Decision date | 24 Jul 2024 |
| Subject to call-in | Yes |