Salford City Council – Record of
Decision
I Paul Dennett, City
Mayor, in exercise of the powers contained within the Council
Constitution do hereby approve:
·
the variation to the contract sum to enable the
building of 21 affordable homes at Tootal
Grove, as detailed in the table below:
Detail required
Answers
Title/Description of Contracted
Service/Supply/Project
Construction of 16 move on units and 19 affordable
homes.
Name of Successful
Contractor
PLP Construction Ltd.
Supplier Registration Number
(to be supplied by Corporate
Procurement)
03244506
Type of organisation
(to be supplied by Corporate
Procurement)
Private Limited Company
Status of Organisation
(to be supplied by Corporate
Procurement)
SME
Contract Value (£)
£
7,377,513
Contract Duration
24 months
Contract Start Date
15/08/2023
Contract End Date
29/08/2025
Optional Extension Period 1
months
Optional Extension Period 2
months
Who will approve each Extension
Period?
Procurement Board (extension >
£150k)
Contact Officer (Name &
number)
KONRAD MAGDINSKI 793 2197
Lead Service Group
Place
How the contract was procured?
(to be supplied by
procurement)
ICN Framework
Framework Details (where
applicable)
(procurement body, framework reference
& title, start/ end date
Innovation Chain
North (ICN) is a framework for construction and associated
professional services procured under the Public Contracts
Regulations 2015 and is OJEU compliant. It has been designed to
support the delivery of new homes and associated social
infrastructure across the North of England. The framework includes
lots for contractors, associated professional services as well as a
Dynamic Purchasing System (DPS) for the supply of Modular
Homes.
Funding Source
Grant
Ethical Contractor (EC): Mayor’s
Employment Charter
?
EC: Committed to sign Charter
?
EC: Accredited Living Wage
Employer
?
The purpose of this
report is to seek approval for a variation the increase in costs to
enable the building of 21 affordable homes at Tootal
Grove.
The
scheme has significant benefits including:
Reducing the use of temporary accommodation, particularly if it
reduces the need to place homeless out of the city and placing
vulnerable residents in permanent accommodation is shown to have
positive impact on health.
RSAP provision will provide valuable move on accommodation with
support for people who have experienced multiple disadvantage and
tenancy failure.
It
will provide valuable, affordable “stepping stone”
accommodation for those who are seeking to address issues within
their life such as mental health challenges, substance misuse,
domestic abuse.
RSAP accommodation acts as a “trial tenancy”. The
length of stay is expected to be up to 2 years which allows the
occupant to prove their tenancy readiness to other landlords. Many
may be bypassed on the register without this positive tenancy
evidence.
Affordable supported accommodation is rare and allows people to
access employment without the burden of high cost supported
accommodation that is the norm within exempt accommodation
schemes.
RSAP units have been designed to be day to day cost effective
for the occupant - leading to financial viability for the occupant
and increasing the sustainability of the tenancy.
Assessment of Risk: High
Without the additional funding
there is a significant risk that that the work will not be able to
be completed.
Future construction risks will then be monitored, and mitigated,
through the project group.
The source of funding
is:
·
Homes England RSAP and Affordable Housing Programme
funding.
·
Capital Programme - Invest to Save and USB capital
grant.
·
Brownfield Land Release Fund.
Legal Advice obtained – The Shared Legal Service
– Tony Hatton.
Financial Advice
obtained Grace Rogerson
– Senior Accountant.
Procurement Advice obtained
Debbie Derbyshire Ext 6244.
Contact Officer: Konrad Magdzinski
Telephone number: 0161 793 2197
This matter is not subject to
consideration by another Lead Member.
The appropriate Scrutiny
Committee to call-in the decision is the Growth and Prosperity
Scrutiny Panel.
Signed: Paul Dennett Dated: 26 June
2024
City Mayor
FOR DEMOCRATIC SERVICES USE
ONLY
*
This decision was published on 7 August 2024
*
This decision will come in force at 4.00 p.m. on 14 August 2024
unless it is called-in in accordance with the Decision Making
Process Rules.
Details
| Outcome | Recommendations Approved |
| Decision date | 26 Jun 2024 |
| Subject to call-in | Yes |