Regeneration Programme & Towns Fund Bi-Annual Update
July 12, 2023 Cabinet (Cabinet collective) Key decision Awaiting outcome View on council websiteFull council record
Decision
Resolved:-
- 1 That the progress made on projects within the Regeneration Project Pipeline Performance Report, including Towns Fund Programme, is received.
- 2 That the following amendments to the Regeneration Project Pipeline are approved:
•Archives Centre, Smethwick project be added to the pipeline.
•Netomnia Full Fibre project be added to the pipeline.
•Brownfield Land One Public Estate (OPE) sites (if approved) be added to the pipeline.
•Breakdown of programmes to articulate individual sites/projects (where appropriate).
- 3 That in connection with 1.2 above, the Director of Regeneration & Growth is authorised to implement the amendments to the Regeneration Project Pipeline and for this to be published on the council website.
Supporting Documents
Details
| Outcome | For Determination |
| Decision date | 12 Jul 2023 |
| Effective from | 20 Jul 2023 |
| Subject to call-in | Yes |