Bootle Canalside - Finance virement phase 2 works

September 22, 2023 Cabinet Member - Regeneration and Skills (Cabinet member) Awaiting outcome View on council website
Full council record

Purpose

The purpose of this report is to seek approval to the virement of funding from the Council’s Growth Budget to the Bootle Canalside (Salt n Tar) Capital programme in the sum of £300,000 to enable the completion of the project as identified and previously approved as part of the Bootle Canalside project Business Case.

Decision

Decision(s):

That a a virement of £300k from the Growth Budget to the Capital Programme 2023/24 be approved.

Reasons for the Decision(s):

To make additional provision within the budget to cover project costs for the Salt n Tar project event space which will deliver economic and social benefits to the residents and businesses of Bootle.

Alternative Options Considered and Rejected: (including any Risk Implications)

Options are:

Do Nothing - not recommended as an option as programme of events has been developed and site has to be completed.

Fund the capital works herein via other funding sources – not recommended given the previous allocation and approval from Cabinet for the use of funds for the project proposed.

Supporting Documents

Bootle Canalside Finance virement phase 2 works.pdf

Details

OutcomeFor Determination
Decision date22 Sep 2023
Effective from3 Oct 2023