Summerhill CP School – Phase 1 Tender Approval For The Expansion of the School to a Two Form Entry
November 6, 2026 Cabinet Member - Children Schools and Families (Cabinet member) Unknown View on council websiteFull council record
Purpose
Due to an increase in the expected number of primary school aged pupils in the Maghull area caused by housing developments, it was determined that Summerhill CP School would be expanded from a one form entry school to a two form entry school. This will entail construction of a two storey classroom block to create an additional eight classrooms as well as refurbishment of existing classrooms and ancillary areas. It also includes alterations and improvements to the external play spaces. This report seeks approval to direct award to the most advantageous bid so that the project can proceed. Cabinet delegated authority to the Cabinet Member to commission procurement of these works in a report dated 19th June 2025.
Decision
Decision(s): That
- the most advantageous bid obtained via a direct award through an approved framework which ensures delivery of the project for the start of the Autumn term 2027 be approved; and
- the Assistant Director Education in consultation with the Cabinet Member for Children’s Schools and Families be granted delegated authority to direct award a contract to the successful contractor resulting from the procurement exercise and for any such contracts to be sealed by Legal and signed by an authorised signatory within Legal.
Reason(s) for the Decision(s):
Included in the Cabinet Revenue & Capital budget report and meeting of the 1st of September 2022 was the approval for the expansion of Summerhill Primary school from a one form entry to a two form entry school. The approved funding for phase 1 of the project is a total of £5,100,210 to undertake the expansion of Summerhill Primary School (420 places) utilising the Section 106 funding of £3,635,273 secured from the housing developers in the local area as well as well an allocation of £1,464,937 from the School Condition Allocation (SCA) capital grant from the DfE.
The total available budget for the project is £5,100,210 for phase 1 of the project which includes a two storey extension to create an additional 8 classrooms as well as creation of a new playground and some minor internal works to the existing accommodation.
It should be noted that phase 2 of the work will need to be funded from future SCA allocations, from savings on existing SCA schemes and from the Basic Needs Capital grant. This will need to have Cabinet approval and will be reported in due course.
Alternative Options Considered and Rejected
N/A
Supporting Documents
Details
| Reference | Call-ins0 |
| Outcome | Awaiting Implementation |
| Decision date | 6 Nov 2026 |
| Effective from | 17 Nov 2026 |
| Subject to call-in | Yes |