Attercliffe LUF/Regeneration Framework Progress Update

September 11, 2024 Transport, Regeneration and Climate Policy Committee (Committee) Approved View on council website
Full council record
Content

10.1

The Senior Development Officer submitted a
report that provided a progress update on the successful Round 1
Levelling Up Fund bid for the Attercliffe Area since 15th  November
2023.

 

 

10.2

RESOLVED UNANIMOUSLY: That the
Transport, Regeneration and Climate Policy Committee notes the
progress made on the Attercliffe Levelling Up Fund project.

 

 

10.3

Reasons for
Decision

 

 

10.3.1

This report provides a progress update on the
successful Round 1 Levelling Up Fund bid for Attercliffe Area on
progress since 15th November 2023.

 

 

10.4

Alternatives
Considered and Rejected

 

 

10.4.1

Do nothing:
Not changing the delivery and development
route for the CCHT would mean that the project couldn’t be
delivered.

 

 

10.4.2

Do More:
To do more would require an increase in
funding. This is not currently required to deliver the required LUF
outputs

 

 

10.4.3

Chosen Options:
The options in the report represent the best
way of delivering the contracted LUF outputs.

 

Supporting Documents

EIA 2433 - Levelling Up Fund - Attercliffe - 2024-09-04 08_46_18.pdf
TRC Attercliffe LUF Report.pdf
Presentation to Committee Attercliffe.pdf

Details

OutcomeRecommendations Approved
Decision date11 Sep 2024