Shropshire Council's Cabinet approved the submission of a planning application for demolition and park construction, and agreed to commence stakeholder engagement on the masterplan on 18/10/2023. The Cabinet delegated responsibility to the Executive Director of Place to finalise the masterplan, planning strategy, and undertake a feasibility study for the Ravens Meadow car park.

Full council record

Decision

RESOLVED:

  1. 1.     That Cabinet:
  2. 1.1. Approved the submission of a planning application for the demolition of the Riverside shopping centre and the former Riverside medical practice, and enabling work, construction of the proposed park and temporary greenspace (as set out in the Council report 6 July 2023), all aligned to the Levelling Up Fund bid award for the Smithfield Riverside Redevelopment Programme (Project 1) of £14.85m.
  3. 1.2. Agreed to commencement of the stakeholder engagement and public consultation programme on the emerging masterplan for Smithfield Riverside.
  4. 2.     Delegated responsibility to the Executive Director of Place, in consultation with the Section 151 Officer and the Portfolio Holders for Climate Change, Environment and Transport, Economic Growth and Regeneration and Housing and Assets, to progress the capital project (item 3.2.1 above), to include, but not limited to, the following:
  5. 2.1. Finalise the masterplan for the wider Smithfield Riverside redevelopment area following the outcomes of the stakeholder engagement and public consultation programme, as provided for in Recommendation 3.1.2 above, and for inclusion in a further report for final approval by Council.
  6. 2.2.  Finalise planning strategy for future phases of development for the Shrewsbury Town Centre Redevelopment Programme: Smithfield Riverside Phase One, following the outcomes of the stakeholder engagement and public consultation programme, as provided for in Recommendation 3.1.2 above, and for inclusion in a further report for final approval by Council
  7. 2.3. Undertake an options and feasibility study for the retention, reconstruction and/or replacement of Ravens Meadow multi-storey car park, necessary to inform future phases of the Smithfield Riverside masterplan, and for inclusion in a further report for final approval by Cabinet and Council.
  8. 3.     That Cabinet agreed to recommend to Council to:
  9. 3.1. Progress the above works as a capital project to completion of contract documentation and receipt of tenders, for demolition, enabling works and construction of the park and associated temporary greenspace within the Levelling Up Fund bid award for the Smithfield Riverside Redevelopment Programme (Project 1) of £14.85m.

Supporting Documents

Shrewsbury Town Centre Redevelopment Programme Phase One-05092023 1253.pdf

Details

OutcomeRecommendations Approved
Decision date18 Oct 2023
Effective from26 Oct 2023